Just a quick look at some of the parts in production at the moment.
the good news is that the foden 6inch cylinder block is getting close. we now have it mounted on the 4th axis and this should allow us to drill all the angled holes at the same time, saving a huge amount of time...
also been working on the 4inch burrell valve motion kit...
and a load of 6inch foden parts...
now starting work on the first kit of the new Showmans batch, the front wheels.
hubs and covers on the lathe...
the good news is that the foden 6inch cylinder block is getting close. we now have it mounted on the 4th axis and this should allow us to drill all the angled holes at the same time, saving a huge amount of time...
also been working on the 4inch burrell valve motion kit...
and a load of 6inch foden parts...
now starting work on the first kit of the new Showmans batch, the front wheels.
hubs and covers on the lathe...
craig@STW- Number of posts : 1410
Location : location Location
Registration date : 2010-05-06
General production update October 2013
Hi Craig,
Many thanks for the update, looking forward to starting building the next batch of Showman's .
Best regards
Steve
Many thanks for the update, looking forward to starting building the next batch of Showman's .
Best regards
Steve
Heavyhaul- Number of posts : 80
Age : 59
Location : Aylesbury, Buckinghamshire
Registration date : 2013-07-01
Re: General production up-date OCTOBER 2013
Any news on the 4.5" cylinder block?
Hecter- Number of posts : 50
Age : 30
Location : Luton
Registration date : 2013-02-13
Re: General production up-date OCTOBER 2013
4.5 foden cylinder blocks will be on as soon as the 6inch ones are done. and they wont take as long as the jigs and programs are all done from before
craig@STW- Number of posts : 1410
Location : location Location
Registration date : 2010-05-06
Re: General production up-date OCTOBER 2013
Hi Craig, thanks for posting the update and the pictures, seeing all the other 6" Foden parts in your photo's - does that mean we will be getting 2 kits this month to make up for not getting anything last month?
HStannard- Number of posts : 58
Location : Rushden, Northants
Registration date : 2011-11-09
Re: General production up-date OCTOBER 2013
just a few pics from this week...
the 6inch foden cylinder blocks were finished and sent out...
and work was started on the 4inch foden blocks...
also doing some work on the showmans flywheels...
and kit 1 of the new showmans batch is coming along well...
the 6inch foden cylinder blocks were finished and sent out...
and work was started on the 4inch foden blocks...
also doing some work on the showmans flywheels...
and kit 1 of the new showmans batch is coming along well...
craig@STW- Number of posts : 1410
Location : location Location
Registration date : 2010-05-06
Re: General production up-date OCTOBER 2013
Oh kit 1 of the. Showmans.
That takes me back 3 years
That takes me back 3 years
lynnr- Number of posts : 3242
Age : 56
Location : Highland, 4inch showman
Registration date : 2010-08-06
Burrell Single Crank Compound update
Thanks for the update Craig, Any update or photos of the Burrell Single Crank Compound kit 1
steamburrell09- Number of posts : 3
Location : TORQUAY, SUNNY DEVON !!!
Registration date : 2009-04-05
Re: General production up-date OCTOBER 2013
Jamie,
The first kit for this engine is not due out until November so all materials have been ordered and have either been delivered or are awaiting the supplier to deliver them (including 20,000 rivet bolts!).
The odd part has been made in the last week or is in production currently (rivet nuts & oilers).
The exception to this is the front wheels that customers chose the option of having them vulcanised. These were manufactured earlier in the month and sent away for rubber bonding as the lead time on this can be a few weeks.
If Craig gets chance i'll ask him to add a couple of photo's later of what has already been done and also open up a SCC group page dedicated to that engine.
Regards
Dean
The first kit for this engine is not due out until November so all materials have been ordered and have either been delivered or are awaiting the supplier to deliver them (including 20,000 rivet bolts!).
The odd part has been made in the last week or is in production currently (rivet nuts & oilers).
The exception to this is the front wheels that customers chose the option of having them vulcanised. These were manufactured earlier in the month and sent away for rubber bonding as the lead time on this can be a few weeks.
If Craig gets chance i'll ask him to add a couple of photo's later of what has already been done and also open up a SCC group page dedicated to that engine.
Regards
Dean
Re: General production up-date OCTOBER 2013
Hey, I saw showman's/road loco flywheels in this update and I have a text from Interlink express today saying something will be delivered tomorrow - probably a box full of cast iron jigsaw puzzle then!!!!
bjwlancashire- Number of posts : 938
Location : Mellor, Lancashire
Registration date : 2010-09-07
Re: General production up-date OCTOBER 2013
Hope yours arrives ok Brian
Mine is coming tommorow too, fingers crossed
Kev
Mine is coming tommorow too, fingers crossed
Kev
Kevster- Number of posts : 424
Location : Hertfordshire 4 inch; DCC road loco
Registration date : 2011-01-27
Re: General production up-date OCTOBER 2013
Mines on the way as well!
Simon
Simon
MrStationHouse- Number of posts : 314
Location : Malmesbury
Registration date : 2011-04-26
Similar topics
» GENERAL PRODUCTION UPDATE: May 2013
» GENERAL PRODUCTION UPDATE- MARCH 2013
» General Production update SEPTEMBER 2013
» GENERAL PRODUCTION UPDATE: April 2013
» general production update: november 2013
» GENERAL PRODUCTION UPDATE- MARCH 2013
» General Production update SEPTEMBER 2013
» GENERAL PRODUCTION UPDATE: April 2013
» general production update: november 2013
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum